Standby Generator Installation and Solar Panel Installation in Leonardo, NJ | 32 Panels Eighteen Months After the Generator

Leonardo, NJ · Client since December 2013

Odete in Leonardo has been a Green Sun Energy Services client since December of 2013. The standby generator was commissioned in February 2014 and the solar array eighteen months after that.

A 17 kW machine in February 2014

The machine is a Generac 17 kW, model 6243, delivering 16 kW on natural gas, which is what this house runs on, behind a 200-amp service-rated transfer switch with two power management modules.

The house is 2,672 square feet and its electrical calculation comes to 15,734 watts. Three thousand watts of air conditioning is managed while the generator is running, leaving 12,734 to hold — comfortably inside what the machine delivers, and well above the 13 kW the code calculation sets as a floor.

It was last serviced on 17 February 2026, which is twelve years after it was commissioned and the more useful of the two facts.

32 panels in September 2015

Thirty-two LG 300-watt panels, 9.6 kW in total, on QuickMount rails with an Enphase M250 microinverter behind each one. Estimated first-year production is 10,556 kWh and the utility is JCP&L.

Two problems, in the order they arrived

Most households on this site bought solar first and backup power later. This one went the other way round, and the sequence is worth drawing out because it makes the distinction between the two systems unusually clear.

In 2013 the question was reliability. The electrical service to this house comes in overhead, which is the arrangement most exposed to weather — a limb on the drop, ice on a span, a pole down two streets away — and the answer to that question is a machine that starts on its own when the supply stops. Solar would have been no answer at all: a grid-tied array disconnects the instant the utility fails, and has to, so that it cannot energise a line a crew is working on.

Eighteen months later the question was different. It was not about outages; it was about how much electricity this household buys from the grid across an ordinary year, and whether some of it could be produced on the roof instead. A generator has nothing to say about that either — it burns gas, it runs a few dozen hours a year, and it makes no difference whatsoever to an ordinary bill.

Two questions, eighteen months apart, with no overlap between them and no substitute available in either direction. What the household ended up with was not one system extended but two systems doing entirely separate work — which is what they were both bought for.

Project Facts

Location
Leonardo, NJ
Services
Solar Panel Installation, Standby Generator Installation, Standby Generator Service
Client since
December 2013

Solar

Panels
LG Model # 300N1C-G3/35mm
Panels
32
System size
9.60 kW
Inverter
EnPhase M250-60-2LL-S22 Micro-Single
Mounting system
QuickMount
Estimated first-year production
10,556 kWh
Share of the home's electricity
73%
Electric utility
JCP&L

Standby generator

Manufacturer
Generac Model # 6243
Rated output
17 kW LP / 16 kW NG
Fuel
Natural Gas
Home sized for
2,672 sq ft
Electrical service
200 amp
Transfer switch
200 amp
Load management
Managed Whole House

Questions from Leonardo homeowners

Standby generatorDoes a propane generator need permits in Leonardo?

A permanently installed propane generator normally requires construction permits, and the propane installation has to satisfy the applicable fuel-gas and LP-gas requirements. Tank placement, capacity, piping, regulators, setbacks and fire-safety provisions all come under review.

SolarWhat does solar offset mean?

It compares the array's estimated annual production with the home's expected annual consumption. A house using 12,000 kWh a year with a system expected to generate 11,400 kWh has a 95 percent offset. It is an annual energy comparison, not a promise that solar supplies 95 percent of the electricity in any given hour.

Standby generatorDoes new gas piping have to be pressure tested in Leonardo?

Yes. Gas piping subject to the adopted fuel-gas code must be inspected and tested before it is accepted. New Jersey adopts the 2024 International Fuel Gas Code, which governs the inspection, the test pressure and how long the test has to hold.