Solar Panel Installation in Toms River, NJ | 39 Panels and 13.65 kW

Toms River, NJ · Client since September 2019

Greg from Toms River, NJ has been a Green Sun Energy Services client since September of 2019. The array was completed in November: 39 panels making 13.65 kW into a SolarEdge HD Wave inverter with optimizers, 226 feet of critter guard around the perimeter, and an estimated 15,221 kilowatt hours in the first year. JCP&L interconnected it in December. Seven years on, the critter guard is the part worth mentioning: the gap between panels and roof is where squirrels and birds nest, and the wiring damage they do is invisible from the ground until production quietly drops. The existing roof was sound enough to take the array as it stood.

Project Facts

Location
Toms River, NJ
Services
Solar Critter Guard, Solar Panel Installation
Client since
September 2019
Panels
LG Model # 350N1C-V5
Panels
39
System size
13.65 kW
Inverter
SolarEdge SE11400H-US000NNC2 HD Wave
Mounting system
Unirac
Estimated first-year production
15,221 kWh
Electric utility
JCP&L
Critter guard fitted
226 ft

Solar questions from Toms River homeowners

How much does shade from mature Toms River trees affect production?

Shade can materially reduce production, particularly when it falls during the highest-production hours. Module-level electronics such as microinverters and optimizers reduce the effect of partial shading, but they cannot create sunlight where there is none. Significant shade should be modelled before any annual production figure is quoted.

What is rapid shutdown?

A code safety requirement intended to reduce hazardous voltage in controlled areas of a rooftop array during an emergency -- so that firefighters are not working around energised conductors. Modern residential systems achieve it with compliant module-level electronics and listed inverter equipment.

Does every solar homeowner receive SREC-II payments?

No. The project has to qualify for and be properly registered in the applicable New Jersey solar incentive programme. Older systems may sit in different programmes altogether, including legacy SREC and transition certificate programmes.