EV Charger Installation

The charger is usually the easy part. What takes the thinking is the panel it connects to, the run from there to wherever the car actually sits, and whether the service coming into the house can carry it. These are chargers we installed at New Jersey homes, and each one names the unit, the circuit it runs on and the electrical service behind it.

90 completed EV charger projects across 74 New Jersey towns, including 8 with a review written by the customer.

EV Charger Installation in Howell, NJ | An 11.5 kW Garage Charger

Alexander from Howell, NJ has been a Green Sun Energy Services client since February of 2025. The charger went into the garage that April: a hardwired ChargePoint Level 2 unit rated 11.5 kW on a dedicated 60-amp circuit, within ten feet of the breaker box. The service measurement came back with 164 amps of spare capacity, which is unusually generous and meant the 60-amp circuit could be added without touching the panel. A garage installation also suits the charger itself: the unit spends its life out of the weather, and the cable is handled indoors rather than in whatever the […]

EV Charger Installation in Freehold, NJ | A NACS Charger Installed

Gabriel from Freehold, NJ has been a Green Sun Energy Services client since October of 2024. The charger went in that November: a ChargePoint Level 2 unit mounted outdoors beside the meter on a dedicated 60-amp circuit. This one carries a NACS connector rather than the older J1772 – the standard Tesla used and the rest of the industry has now adopted, so a charger specified this way suits the cars being sold today rather than the ones sold five years ago. The service was measured beforehand and had the capacity to take the circuit, which is the check that

EV Charger Installation in Princeton, NJ | A ChargePoint Charger

Amy from Princeton, NJ has been a Green Sun Energy Services client since October of 2025. The charger went into the garage that November: a ChargePoint Level 2 unit rated 7.7 kW on a dedicated 40-amp circuit, installed within ten feet of the breaker box, with load management fitted alongside it. The load management module is the part worth understanding on a 40-amp installation: rather than requiring a larger service, it lets the charger draw what is available and step back when the house needs the capacity elsewhere. A utility rebate application was filed and closed as part of the

Standby Generator, Solar and EV Charger Installation in Cream Ridge, NJ | A Charger

Chris from Cream Ridge, NJ has been a Green Sun Energy Services client since August of 2019. The generator and the array were bought together and went in five days apart; the charger followed four years later. A 22 kW Generac, and two well pumps: Commissioned on 23 October 2019. The calculation asked for a minimum of 17 kW under NEC Article 220 Part IV and a Generac rated 19.5 kW on natural gas went in – 22 kW were it running on propane – behind a 200-amp managed whole-house transfer switch. The load survey lists 2,900 square feet, two

EV Charger Installation in West Orange, NJ | A ChargePoint Charger

Nicholas from West Orange, NJ has been a Green Sun Energy Services client since September of 2025. The charger went in that November: a hardwired ChargePoint Level 2 unit rated 11.5 kW, mounted outdoors beside the meter on a dedicated 60-amp circuit. The service measurement on this one is the detail worth noting – it came back with 47 amps of spare capacity, which is real headroom but not unlimited, and it is exactly the sort of figure that decides whether a 60-amp charger circuit can be added as it stands or whether the panel has to be dealt with

EV Charger Installation in Warren, NJ | A ChargePoint Level 2 Charger

Eric from Warren, NJ has been a Green Sun Energy Services client since September of 2023. The charger went into the garage that October: a ChargePoint Level 2 unit rated 11.5 kW on a dedicated 60-amp circuit, installed within ten feet of the breaker box. The service was measured first and had ample headroom for the addition, which is the check that decides whether a charger install is a morning’s work or turns into a panel upgrade. When the charger stopped responding the following summer, it was diagnosed and resolved remotely by phone rather than with a truck roll –

EV Charger Installation in New Brunswick, NJ | A NACS Charger Installed

Rodney from New Brunswick, NJ has been a Green Sun Energy Services client since April of 2024. The charger went in that May: a ChargePoint Level 2 unit rated 11.5 kW, mounted outdoors beside the meter on a dedicated 60-amp circuit. This one is a NACS connector rather than the older J1772 – the standard Tesla used and the rest of the industry has now adopted, which means a charger specified this way suits the cars being sold today rather than the ones sold five years ago. The service was measured before anything was ordered and had the capacity to

EV Charger Installation in Carteret, NJ | A ChargePoint Level 2 Charger

David from Carteret, NJ has been a Green Sun Energy Services client since November of 2023. The charger went in that December: a hardwired ChargePoint Level 2 unit rated 11.5 kW, mounted outdoors on a dedicated 60-amp circuit run from the panel. The service was measured before anything was ordered and had the headroom to carry it, which is the step that decides whether a charger install is straightforward or turns into a panel upgrade. Sixty amps is a substantial addition to a house, and finding out that the service cannot take it after the equipment has arrived is an

Standby Generator Installation and EV Charger Installation in Manansquan, NJ | A 16 kW Generator in 2021, an EV Charger in 2025

Peter from Manasquan, NJ has been a Green Sun Energy Services client since August of 2020. The generator went in that winter; the car charger followed nearly five years later. A 16 kW Generac on a managed whole-house switch: Commissioned on 6 January 2021. The calculation asked for a minimum of 15 kW under NEC Article 220 Part IV and a 16 kW Generac Guardian went in on natural gas, behind a 200-amp managed whole-house transfer switch with two smart management modules. The house is 3,000 square feet with two refrigerators, a dishwasher, a washer, a gas dryer and a

EV Charger Installation in North Brunswick, NJ | A Tesla Universal Wall Connector

Delavar from North Brunswick, NJ has been a Green Sun Energy Services client since November of 2024. The charger went into the garage in January of 2025: a Tesla Universal Wall Connector, third generation and hardwired, 48 amps and 11.5 kW on a dedicated 60-amp circuit, with surge protection on the charger circuit. The Universal model is the one worth knowing about – it carries a built-in J1772 adapter, so it charges a Tesla and any other electric car on the market without a dongle hanging off the end of the cable. That matters more than it sounds when the

EV Charger Installation in Middletown, NJ | A ChargePoint Level 2 Charger

Christelle from Middletown, NJ has been a Green Sun Energy Services client since September of 2024. The charger went in that October: a hardwired ChargePoint Level 2 unit rated 11.5 kW, mounted outdoors and fed by a dedicated 60-amp circuit run from the main panel. Before any of that, the service was measured to see what it could actually carry, and it came back with room for the charger without crowding everything else in the house. That check is the difference between a charger that works every night and a panel that trips whenever the car and the dryer run

EV Charger Installation in Pennington, NJ | Tesla Wall Connector Installed

Seyhan from Pennington, NJ has been a Green Sun Energy Services client since September of 2024. In November of that year we installed a Tesla Wall Connector outdoors at the house – the third generation hardwired unit, 48 amps and 11.5 kW, on a dedicated 60-amp circuit run up from the panel in the basement. The figure that decides a job like this is the one nobody ever sees: the service was carrying enough spare capacity to take a 60-amp charger circuit without being pushed past its limit. A charger pulling that much for hours at a stretch is the

Scroll to Top